Reading a Moroccan house construction quote from abroad: a 2026 worked example

By , architect · Updated on · Reference texts (4)

Free, no account and no contact details.

You live abroad and a Moroccan builder has sent you a quote, often in French, full of abbreviations (DQE, BPU, HT, TTC, situation, retenue de garantie). This guide decodes it, shows a complete priced example from the CITURBAREA cost estimator, and explains how to compare three quotes and pay in stages without being on site.

In short: a good construction quote is a priced bill of quantities (bordereau des prix et détail quantitatif, DQE): one line per item, with unit, quantity, unit price and amount, grouped by trade package. Example calculated by the CITURBAREA cost estimator for a two-storey (R+1) 150 m² house in mid-range finish in Kénitra: 645,265 DH excluding VAT of works in 18 packages, 813,034 DH including VAT with a 5% contingency and VAT, i.e. 5,420 DH per m² including VAT. The structural work (packages 00 to 05) accounts for 53% of it.

Detail in the estimator →

Your budget, calculated for your project

Overall estimate by trade in 2 minutes, free and with no commitment, then a free video call with a registered architect. The detailed cost study (bill of quantities) is included in a full architectural design assignment; ordered on its own, it is paid.

Estimate my project → Start my file

📹 Free video call with the architect →

The words on a Moroccan quote, translated

On the quoteWhat it meansWhat to do with it
Devis / DQE (détail quantitatif estimatif)Priced bill of quantities: item, unit, quantity, unit price, amountInsist on it; a lump sum per m² cannot be checked
BPU (bordereau des prix unitaires)List of unit prices that will apply to quantities actually builtLets extras and omissions be priced fairly
Lot / corps d'étatTrade package (earthworks, concrete, plumbing…)Compare quotes package by package
HT / TVA / TTCExcluding VAT / VAT (20 %) / including VATBring all quotes back to HT before comparing
Situation de travauxInterim valuation of work doneThe only basis for a payment; have it checked first
Retenue de garantieRetention kept from each payment until handoverWrite the rate and release terms in the contract
AvenantWritten, priced amendment for extra workNo extra work without one, signed before it starts
PV de réception (avec réserves)Handover record (with a snag list)Release the retention only when the snags are cleared
ICE / RCCompany identifier / trade register numberCheck the company exists before signing

What does a good house construction quote look like?

A serious quote reads like a technical document, not like a sales offer. It contains, in this order:

  1. Identification: company (legal name, ICE company identifier, trade register number, address), project owner, address of the plot, references of the permit and of the drawings used.
  2. Assumptions: type of foundation, concrete class, slab thickness, finish level, what is excluded.
  3. Detail by package: each item with unit (m³, m², linear metre, unit), quantity, unit price excluding VAT and amount.
  4. Summary: total excluding VAT per package, total excluding VAT, VAT, total including VAT.
  5. Conditions: deadline, payment schedule, retention, penalties, validity of the offer.

A one-page quote saying "turnkey house: 4,000 DH/m²" allows you neither to compare, nor to check, nor to settle a dispute.

Your budget, calculated for your project

Overall estimate by trade in 2 minutes, free and with no commitment, then a free video call with a registered architect. The detailed cost study (bill of quantities) is included in a full architectural design assignment; ordered on its own, it is paid.

Estimate my project → Start my file

📹 Free video call with the architect →

Priced example: a 150 m² two-storey house

This summary comes from the CITURBAREA cost estimator (2026 prices): a house attached on two sides, 75 m² footprint, 3 bedrooms, 2 bathrooms, good soil, mid-range finish, city of Kénitra, general contractor.

Members only

Priced quote, package by package

The full summary for a 150 m² two-storey house: amount excl. VAT and share of each of the 18 work packages, from site set-up to external drainage, then contingencies, VAT and total incl. VAT.

Free account, newsletter and YouTube channel

CITURBAREA cost estimator, version 2026-10. Quantities from a parametric take-off: an order of magnitude from the simulator, with no guaranteed accuracy; with drawings, they become measured quantities.

This summary excludes the land, the fees (64,267 DH including VAT for a full architect's assignment, the engineering consultancy (BET), the soil survey, the surveyor and the laboratory), the permit taxes (8,118 DH) and the utility connections (about 12,500 DH). The full budget therefore reaches 897,919 DH. Prices per m² are detailed in our guide on house construction cost per m².

Extract from the bill: what do the lines look like?

PackageItemUnitQuantityUnit price excl. VATAmount excl. VAT
02Reinforced concrete for isolated footingsm³9.752,32722,692
02Reinforced ground-bearing slab 12 cmm²7527520,621
03Hollow-block floor 16+4, completem²13540554,714
03Reinforced concrete for beams, ring beams, lintelsm³6.04,08724,522
04Wall in 20 cm concrete blocksm²218.619742,967
04Interior cement plasterm²464.86027,872
05Two-layer SBS waterproofingm²7514510,854
08Thermally broken aluminium double-glazed windows, installedm²19.11,61230,844
1360×60 porcelain stoneware tiles, gluedm²13228637,800
16Standard bathroom fittingsunit26,96013,920
17Recessed 2P+E socket outletunit382439,223

Each unit price includes supply, installation, overheads and the company's margin. For the detail of structural-work prices and of concrete and steel quantities, see structural work cost in Morocco.

What about a 100 m² house?

Same assumptions, 100 m² of floor area on two levels: 493,560 DH excluding VAT of works and 621,885 DH including VAT in mid-range finish (6,219 DH including VAT per m²), 689,601 DH for the full budget. In very economical finish with a tâcheron (labour-only contractor), the works drop to 368,979 DH including VAT. The m² is more expensive than at 150 m² because the kitchen, bathrooms, staircase and electrical panel do not shrink with the floor area. On a 100 m² plot, see house plan on 100 m².

How do you compare three quotes?

  1. Have the same quantities priced. Give each company the same bill, prepared by the architect or taken from the estimator. Otherwise you are comparing different projects.
  2. Bring everything back to amounts excluding VAT, then apply VAT yourself. Check whether the company charges VAT and on what.
  3. Compare package by package, then line by line. A quote 15% cheaper overall often hides a forgotten package (waterproofing, drainage, low-voltage systems) or reduced quantities.
  4. Spot differences of more than 20% on a unit price compared with the estimator's reference or the average of the quotes. That is the threshold the CITURBAREA engine uses to flag a price that needs justifying.
  5. Check how the work is done. A tâcheron who prices only labour cannot be compared with a company that supplies everything. On this house, the estimator gives 580,344 DH including VAT with a tâcheron against 813,034 DH with a company, but with a tâcheron the purchasing and coordination are yours.

How do you pay a Moroccan builder from abroad?

On CITURBAREA, situations and invoices are validated by the client before payment and every exchange stays on the platform; no phone numbers are exchanged between parties.

Which clauses should you require in the contract?

What are the warning signs?

To check a company before signing, read how to choose a construction company. For items outside the works, see architect fees and building permit fees and taxes.

How do you get your own reference quote?

Enter your project in the estimator: you get a bill of quantities package by package, with unit prices and ranges, to hand to companies as the basis for tendering. Once you have the drawings and the zoning information certificate, measured quantities replace the ratios and the figure is refined, together with the soil survey and contractors' tenders.

Frequently asked questions

What does a house construction quote look like in Morocco?

A good quote is a priced bill of quantities: each item is described with its unit, quantity, unit price excluding VAT and amount, grouped by package (earthworks, foundations, reinforced concrete, masonry, waterproofing, joinery, plumbing, electrics…), then summarised excluding VAT, VAT and including VAT.

How much does a 150 m² house cost according to a typical quote?

The CITURBAREA estimator gives 645,265 DH excluding VAT of works for a two-storey 150 m² house in mid-range finish in Kénitra, i.e. 813,034 DH including VAT with a 5% contingency and VAT. Excluding land, fees, taxes and utility connections.

What quote for a 100 m² house?

For 100 m² of floor area on two levels in Kénitra, the estimator gives 621,885 DH including VAT of works in mid-range finish and 368,979 DH including VAT in very economical finish with a tâcheron.

How do you compare several construction quotes?

Have each company price the same quantities, bring everything back to amounts excluding VAT, compare package by package then line by line, and ask for a written justification for any unit price more than 20% away from the reference.

What deposit should you pay a construction company?

As little as possible and never without a contract. LesMRE recommends never exceeding 30% in advance and spreading payments according to the actual progress of the works.

What is a retention (retenue de garantie)?

A share of each payment kept by the client until the works are accepted without reservations. LesMRE cites a retention of 5 to 10%. It must appear in the contract with its release terms.

Can I sign and follow a Moroccan building contract from abroad?

Yes. The contract, situations and invoices can be exchanged and validated remotely; what you cannot do remotely is check the work, so the architect's site supervision and dated photos at each milestone replace your visits.

Is the quote price fixed?

It depends on the contract. With a bill of quantities and unit prices (DQE / BPU), the final price follows the quantities actually built; with a lump-sum price, it is fixed for the described scope, and any change goes through a written amendment.

Reference texts (4)

Start my fileWhatsAppAppeler

Read next

All guides → · Standards library →

Stay informed

Material prices, new planning rules and site advice: one letter a month, written by an architect.

▶ Subscribe to the YouTube channel Channel of architect Yassine AT-TARASSI: sites, prices and procedures on video.
Create my free account →

Create your free account to continue

Supplier prices, technical data sheets and product comparison are reserved for account holders. The account is free and takes a minute.

Create my free account → I already have an account

I am a professional

Become a member, for free

Three steps, only once. After that, the members-only content of every guide opens here, without reloading the page.

  1. 1. Create an account or sign in

    The account is free. After signing up, you come back to this guide.

    Create my free account → I already have an account I am a professional

  2. 2. Subscribe to the newsletter

    Tick the box to give your consent, then confirm.

  3. 3. Subscribe to the YouTube channel

    CITURBAREA cannot check a YouTube subscription: your statement is recorded with your account.

    ▶ Subscribe on YouTube

Ce contenu est consultable uniquement en ligne sur citurbarea.com. هذا المحتوى متاح فقط على الموقع citurbarea.com