How long does a building permit take in Morocco? Review, deadlines and appeals from abroad

By , architect · Updated on · Reference texts (6)

You live abroad, your architect has filed the application in Morocco: how long should it take, who holds the file, and what can you do from a distance if nothing happens? This guide follows an application after filing. For the list of documents, see the building permit guide; for online filing, see Rokhas.

In short: once a complete application is filed, the municipality has a regulatory time limit of 15 days for a "small project" (housing up to ground + 3 floors and 15.50 m) and 30 days for a "major project" (taller buildings, shops, public-facing buildings, subdivisions), set step by step by joint order no. 1839-23 of 2023. The clock restarts from zero if the committee asks for amended plans (general building regulations, "RGC", art. 41). Without an answer, the permit is deemed granted two months after filing (Law 12-90, art. 48), but never start work without a written document. A refusal must state its reasons (RGC art. 40) and can be challenged before the administrative court, in principle within 60 days. You do not need to travel for any of these steps: you, your architect or a person you mandate can file (RGC art. 34).

Your permit, prepared by an architect

A registered architect studies your plot, draws the plans and files your application. First call with no commitment.

Start my file → Estimate my project

📹 Free video call with the architect →

Small or major project: which time limit applies?

The category of the application, defined in article 17 and annexes 2 to 4 of the RGC (decree no. 2-18-577 of 2019), sets the time limit, the route and who sits on the review committee.

CategoryTypical projectsTotal regulatory time limit
Small projects (RGC art. 19, annex 3)Housing ≤ 15.50 m and ≤ ground + 3 floors, all rooftop structures included; ≤ 18.50 m and ≤ ground + 4 in a subdivision whose infrastructure has been accepted or in a restructured informal subdivision; extra storeys, alterations and demolition of such buildings15 days (order 1839-23, annex 4)
Major projects (RGC art. 18, annex 2)Subdivisions, housing groups, land division; public buildings; buildings open to the public; business premises; housing above the thresholds; medinas, ksour, kasbahs, listed buildings; regularisations; anything not classed as a small project30 days (order 1839-23, annex 4)
Minor repairs (RGC art. 20, annex 4)Small works with no change of use, structure, façade or internal layout10 working days — see renovation permit

Investor's trap: a shop on the ground floor of a family house turns a small project into a major one and doubles the time limit. Ask your architect to confirm the category before filing.

Who holds the file, step by step

Order 1839-23 sets the time allowed to each party. When you chase a file from abroad, this table tells you who to ask.

StepWho actsMajor projectsSmall projectsSource
Filing receiptMunicipal registry or one-stop shop1 day1 dayOrder 1839-23; RGC art. 34
Transmission to the committeeMunicipality3 days7 days (transmission and review)Order 1839-23; RGC art. 18-19
Review by the committeeProvince or prefecture, municipality, Urban Agency (+ utilities for major projects)15 daysOrder 1839-23; RGC art. 18, 22
Minutes sent to the mayorCommittee secretariat3 days2 daysOrder 1839-23; RGC art. 38
Applicant informedMunicipality3 days2 daysOrder 1839-23; RGC art. 41
Decision and issuePresident of the municipal council5 days3 daysOrder 1839-23; RGC art. 43-44
Total30 days15 daysJoint order 1839-23

Your permit, prepared by an architect

A registered architect studies your plot, draws the plans and files your application. First call with no commitment.

Start my file → Estimate my project

📹 Free video call with the architect →

A dated example: planning your trip around the permit

Two fictitious complete applications filed on Monday 2 November 2026. Cautious assumption: we count working days (the RGC expresses step limits in working days: art. 18, 38, 41, 42, 44), excluding weekends and the national holidays of 6 November (Green March) and 18 November (Independence Day).

StepTwo-storey villa (small project)Ground + 5 apartment block (major project)
Complete application filedMon 2 NovMon 2 Nov
Filing receipt (latest)Tue 3 NovTue 3 Nov
Sent to the committeeFri 13 Nov (transmission and review)Mon 9 Nov
End of committee reviewTue 1 Dec
Minutes to the mayorTue 17 NovFri 4 Dec
Applicant informedFri 20 NovWed 9 Dec
Decision and issue (latest)Wed 25 NovWed 16 Dec
Deemed granted if no answer (Law 12-90 art. 48)Sat 2 January 2027 (two calendar months)
Foundations must start (Law 12-90 art. 49)within one year of issue

Indicative calendar computed by CITURBAREA from joint order 1839-23 and the RGC; the date on your filing receipt prevails. A request for amended plans restarts the count.

For a summer visit, the practical lesson is simple: file complete plans at least two to three months before you want work to begin, so that a request for amendments, the tax payment and the site-opening formalities still fit before you arrive. For the full timeline including design, see the building permit guide.

Working days or calendar days?

Every count starts from the filing receipt of a complete application (RGC art. 34). Ask your architect to send you a copy the day it is issued.

Following your application from abroad

Before filing, the two habits that save the most time: request the zoning information certificate (issued in two working days, RGC art. 7) and have the architect check height, setbacks and plot ratio. A missing main document makes the application inadmissible; a missing supplementary document can never justify a refusal (art. 37).

Members only

Tick-box checklist for the permit file

A printable checklist restates, box by box, the main and supplementary documents and the site-opening formalities described in this guide, so you can check the file before filing it.

Free account, newsletter and YouTube channel

What if…? Situations after filing

SituationEffect on the time limitWhat you can doSource
A main document is missingApplication inadmissible: no clockComplete and refile; keep the new receiptOrder 337-20; RGC art. 34, 37
Minor reservationArchitect has 5 working daysHave documents signed in advanceRGC art. 42
Amended plans requestedRegistered letter within 2 working days; clock restarts when corrected plans are filedCorrect only the points in the minutesRGC art. 41
No answerDeemed granted after two monthsAsk for a written answer; do not start without a document; the governor can issue a formal noticeLaw 12-90 art. 48; RGC art. 55
RefusalReasoned decisionCorrect and refile, request a re-examination, or appealRGC art. 40; circular 2168 (2023); Law 41-90 art. 23
Foundations not started within a yearPermit lapses, no extensionNew application with the previously approved planLaw 12-90 art. 49
You change the projectNew application, new time limitFile amended plans before building; any façade change needs a permitRGC annex 7; Law 12-90 art. 40

Who decides, and whose opinion counts?

Permanent members: province or prefecture, municipality, Urban Agency (RGC art. 22); utilities and telecoms join for major projects. Non-permanent members are limited to administrations whose opinion a text requires (art. 26), such as civil protection (decree 2-92-832, art. 32). The Urban Agency's opinion is binding: the mayor must consult it and comply with its content (art. 39). Law 64-23 (Official Bulletin no. 7533, 10 August 2026) creates regional planning and housing agencies that will take over this role as they are set up.

Tacit approval: can you rely on it?

Under article 48 of Law 12-90, the permit is deemed granted two months after filing if the mayor does not answer. Decree 2-22-141 (2023), implementing Law 55-19, reportedly also lists the building permit among acts where silence means approval, with a certificate from the wali or governor (known from press reports; decree text not reviewed). From abroad, do not rely on it: a tacit permit does not exempt you from the zoning plan, and a bank, notary or the local authority will ask for a document. If the municipality delays, the governor can serve formal notice and act (RGC art. 55; organic law 113-14, art. 76).

Refusal: re-examination or appeal?

Read the minutes first. A technical reason (height, setback, missing document) is usually fastest fixed by refiling corrected plans. The ministry has asked for re-examination of applications without a favourable opinion (circular no. 2168 of 2023). If you consider the refusal unlawful, an action for abuse of power can be brought before the administrative court, in principle within 60 days of notification (Law 41-90, art. 23); a Moroccan lawyer will confirm the deadline for your case.

After the permit: deadlines that keep running

An architect registered with the Order is a condition of the permit in urban municipalities, delimited centres and their outskirts (Law 12-90, art. 50); for 150 m² of floor area or less, only for the design (art. 54). In rural areas, see the rural building permit. For your budget, see the cost simulator.

Actual practice, one-stop-shop arrangements and locally requested documents may vary by municipality and Urban Agency. Check with them before filing.

Every requirement, article by article, with phase, document and responsible party: regulatory requirements matrix for construction in Morocco (in French, table and CSV).

Frequently asked questions

How long does a building permit take in Morocco?

Joint order 1839-23 of 2023 sets 15 days for small projects (housing up to ground + 3 floors and 15.50 m) and 30 days for major projects, counted from the receipt of a complete application. The clock restarts if amended plans are requested (RGC art. 41).

Do I need to be in Morocco to apply for a building permit?

No. The application can be filed by the owner, the architect or a mandated person (RGC art. 34); in practice the architect files online. Keep copies of the filing receipt, the committee minutes and the issued permit.

Is silence from the municipality a permit?

Article 48 of Law 12-90 deems the permit granted two months after filing without an answer. The project must still comply with planning rules: never start work without a written document.

What happens if the committee asks for changes?

You are informed by registered letter within 2 working days and the time limits only restart when corrected plans are filed (RGC art. 41). For a minor reservation, the architect has 5 working days (art. 42).

How long is a building permit valid?

One year: it lapses if foundation work has not started within a year of issue (Law 12-90, art. 49). No extension is provided; you must reapply.

Can I appeal a refusal from abroad?

Yes. The refusal must state its reasons. You can refile corrected plans, request a re-examination, or bring an action for abuse of power before the administrative court, in principle within 60 days of notification (Law 41-90), through a Moroccan lawyer.

Is the Urban Agency's opinion binding?

Yes. Under article 39 of the RGC, no permit can be issued without the Urban Agency's opinion, and the mayor must comply with it.

Reference texts (6)

Start my fileWhatsAppAppeler

Read next

All guides → · Standards library →

Stay informed

Material prices, new planning rules and site advice: one letter a month, written by an architect.

▶ Subscribe to the YouTube channel Channel of architect Yassine AT-TARASSI: sites, prices and procedures on video.
Create my free account →

Create your free account to continue

Supplier prices, technical data sheets and product comparison are reserved for account holders. The account is free and takes a minute.

Create my free account → I already have an account

I am a professional

Become a member, for free

Three steps, only once. After that, the members-only content of every guide opens here, without reloading the page.

  1. 1. Create an account or sign in

    The account is free. After signing up, you come back to this guide.

    Create my free account → I already have an account I am a professional

  2. 2. Subscribe to the newsletter

    Tick the box to give your consent, then confirm.

  3. 3. Subscribe to the YouTube channel

    CITURBAREA cannot check a YouTube subscription: your statement is recorded with your account.

    ▶ Subscribe on YouTube

Ce contenu est consultable uniquement en ligne sur citurbarea.com. هذا المحتوى متاح فقط على الموقع citurbarea.com