How long does a building permit take in Morocco? Review, deadlines and appeals from abroad
By Yassine AT-TARASSI, architect · Updated on · Reference texts (6)
You live abroad, your architect has filed the application in Morocco: how long should it take, who holds the file, and what can you do from a distance if nothing happens? This guide follows an application after filing. For the list of documents, see the building permit guide; for online filing, see Rokhas.
In short: once a complete application is filed, the municipality has a regulatory time limit of 15 days for a "small project" (housing up to ground + 3 floors and 15.50 m) and 30 days for a "major project" (taller buildings, shops, public-facing buildings, subdivisions), set step by step by joint order no. 1839-23 of 2023. The clock restarts from zero if the committee asks for amended plans (general building regulations, "RGC", art. 41). Without an answer, the permit is deemed granted two months after filing (Law 12-90, art. 48), but never start work without a written document. A refusal must state its reasons (RGC art. 40) and can be challenged before the administrative court, in principle within 60 days. You do not need to travel for any of these steps: you, your architect or a person you mandate can file (RGC art. 34).
Your permit, prepared by an architect
A registered architect studies your plot, draws the plans and files your application. First call with no commitment.
Small or major project: which time limit applies?
The category of the application, defined in article 17 and annexes 2 to 4 of the RGC (decree no. 2-18-577 of 2019), sets the time limit, the route and who sits on the review committee.
| Category | Typical projects | Total regulatory time limit |
|---|---|---|
| Small projects (RGC art. 19, annex 3) | Housing ≤ 15.50 m and ≤ ground + 3 floors, all rooftop structures included; ≤ 18.50 m and ≤ ground + 4 in a subdivision whose infrastructure has been accepted or in a restructured informal subdivision; extra storeys, alterations and demolition of such buildings | 15 days (order 1839-23, annex 4) |
| Major projects (RGC art. 18, annex 2) | Subdivisions, housing groups, land division; public buildings; buildings open to the public; business premises; housing above the thresholds; medinas, ksour, kasbahs, listed buildings; regularisations; anything not classed as a small project | 30 days (order 1839-23, annex 4) |
| Minor repairs (RGC art. 20, annex 4) | Small works with no change of use, structure, façade or internal layout | 10 working days — see renovation permit |
Investor's trap: a shop on the ground floor of a family house turns a small project into a major one and doubles the time limit. Ask your architect to confirm the category before filing.
Who holds the file, step by step
Order 1839-23 sets the time allowed to each party. When you chase a file from abroad, this table tells you who to ask.
| Step | Who acts | Major projects | Small projects | Source |
|---|---|---|---|---|
| Filing receipt | Municipal registry or one-stop shop | 1 day | 1 day | Order 1839-23; RGC art. 34 |
| Transmission to the committee | Municipality | 3 days | 7 days (transmission and review) | Order 1839-23; RGC art. 18-19 |
| Review by the committee | Province or prefecture, municipality, Urban Agency (+ utilities for major projects) | 15 days | Order 1839-23; RGC art. 18, 22 | |
| Minutes sent to the mayor | Committee secretariat | 3 days | 2 days | Order 1839-23; RGC art. 38 |
| Applicant informed | Municipality | 3 days | 2 days | Order 1839-23; RGC art. 41 |
| Decision and issue | President of the municipal council | 5 days | 3 days | Order 1839-23; RGC art. 43-44 |
| Total | 30 days | 15 days | Joint order 1839-23 |
Your permit, prepared by an architect
A registered architect studies your plot, draws the plans and files your application. First call with no commitment.
A dated example: planning your trip around the permit
Two fictitious complete applications filed on Monday 2 November 2026. Cautious assumption: we count working days (the RGC expresses step limits in working days: art. 18, 38, 41, 42, 44), excluding weekends and the national holidays of 6 November (Green March) and 18 November (Independence Day).
| Step | Two-storey villa (small project) | Ground + 5 apartment block (major project) |
|---|---|---|
| Complete application filed | Mon 2 Nov | Mon 2 Nov |
| Filing receipt (latest) | Tue 3 Nov | Tue 3 Nov |
| Sent to the committee | Fri 13 Nov (transmission and review) | Mon 9 Nov |
| End of committee review | Tue 1 Dec | |
| Minutes to the mayor | Tue 17 Nov | Fri 4 Dec |
| Applicant informed | Fri 20 Nov | Wed 9 Dec |
| Decision and issue (latest) | Wed 25 Nov | Wed 16 Dec |
| Deemed granted if no answer (Law 12-90 art. 48) | Sat 2 January 2027 (two calendar months) | |
| Foundations must start (Law 12-90 art. 49) | within one year of issue | |
Indicative calendar computed by CITURBAREA from joint order 1839-23 and the RGC; the date on your filing receipt prevails. A request for amended plans restarts the count.
For a summer visit, the practical lesson is simple: file complete plans at least two to three months before you want work to begin, so that a request for amendments, the tax payment and the site-opening formalities still fit before you arrive. For the full timeline including design, see the building permit guide.
Working days or calendar days?
- Step limits (transmission, review, minutes, notification): working days under the RGC.
- Administrative silence: two months from filing (Law 12-90, art. 48), calendar months.
- Permit validity: one year from issue, or from the end of the two-month silence period (art. 49).
- Court appeal: in principle 60 days from notification of a refusal (Law 41-90, art. 23).
Every count starts from the filing receipt of a complete application (RGC art. 34). Ask your architect to send you a copy the day it is issued.
Following your application from abroad
- Who files: you, your architect or a person you mandate (RGC art. 34). In practice the architect files through the electronic platform provided by joint order 338-20 (Rokhas).
- What to ask for: the filing receipt, the committee minutes (they list each member's opinion), any registered letter requesting changes, and the issued permit with plans stamped "ne varietur" (RGC art. 43).
- Reacting quickly: for a minor reservation the architect has only 5 working days (art. 42). Sign in advance whatever the architect may need, so that the file does not wait for your next trip.
- Through CITURBAREA: CITURBAREA is a digital platform published by HSE DECO; architectural services are provided by Arc Bati Architecture, a licensed firm based in Kénitra, or by another licensed architect chosen on the platform, who reports each step to you there; documents and messages stay in your project space.
Before filing, the two habits that save the most time: request the zoning information certificate (issued in two working days, RGC art. 7) and have the architect check height, setbacks and plot ratio. A missing main document makes the application inadmissible; a missing supplementary document can never justify a refusal (art. 37).
Members only
Tick-box checklist for the permit file
A printable checklist restates, box by box, the main and supplementary documents and the site-opening formalities described in this guide, so you can check the file before filing it.
Free account, newsletter and YouTube channel
What if…? Situations after filing
| Situation | Effect on the time limit | What you can do | Source |
|---|---|---|---|
| A main document is missing | Application inadmissible: no clock | Complete and refile; keep the new receipt | Order 337-20; RGC art. 34, 37 |
| Minor reservation | Architect has 5 working days | Have documents signed in advance | RGC art. 42 |
| Amended plans requested | Registered letter within 2 working days; clock restarts when corrected plans are filed | Correct only the points in the minutes | RGC art. 41 |
| No answer | Deemed granted after two months | Ask for a written answer; do not start without a document; the governor can issue a formal notice | Law 12-90 art. 48; RGC art. 55 |
| Refusal | Reasoned decision | Correct and refile, request a re-examination, or appeal | RGC art. 40; circular 2168 (2023); Law 41-90 art. 23 |
| Foundations not started within a year | Permit lapses, no extension | New application with the previously approved plan | Law 12-90 art. 49 |
| You change the project | New application, new time limit | File amended plans before building; any façade change needs a permit | RGC annex 7; Law 12-90 art. 40 |
Who decides, and whose opinion counts?
Permanent members: province or prefecture, municipality, Urban Agency (RGC art. 22); utilities and telecoms join for major projects. Non-permanent members are limited to administrations whose opinion a text requires (art. 26), such as civil protection (decree 2-92-832, art. 32). The Urban Agency's opinion is binding: the mayor must consult it and comply with its content (art. 39). Law 64-23 (Official Bulletin no. 7533, 10 August 2026) creates regional planning and housing agencies that will take over this role as they are set up.
Tacit approval: can you rely on it?
Under article 48 of Law 12-90, the permit is deemed granted two months after filing if the mayor does not answer. Decree 2-22-141 (2023), implementing Law 55-19, reportedly also lists the building permit among acts where silence means approval, with a certificate from the wali or governor (known from press reports; decree text not reviewed). From abroad, do not rely on it: a tacit permit does not exempt you from the zoning plan, and a bank, notary or the local authority will ask for a document. If the municipality delays, the governor can serve formal notice and act (RGC art. 55; organic law 113-14, art. 76).
Refusal: re-examination or appeal?
Read the minutes first. A technical reason (height, setback, missing document) is usually fastest fixed by refiling corrected plans. The ministry has asked for re-examination of applications without a favourable opinion (circular no. 2168 of 2023). If you consider the refusal unlawful, an action for abuse of power can be brought before the administrative court, in principle within 60 days of notification (Law 41-90, art. 23); a Moroccan lawyer will confirm the deadline for your case.
After the permit: deadlines that keep running
- Pay the construction tax shown on the receipt: see permit fees and taxes.
- Site-opening declaration signed by the architect, filed 48 hours before work starts, plus hoarding and site sign (Law 12-90, art. 54-1).
- Site logbook kept by the architect (art. 54-2); failure is fined 5,000 to 10,000 DH (art. 76).
- Foundations within one year (art. 49); at the end, the occupancy permit.
An architect registered with the Order is a condition of the permit in urban municipalities, delimited centres and their outskirts (Law 12-90, art. 50); for 150 m² of floor area or less, only for the design (art. 54). In rural areas, see the rural building permit. For your budget, see the cost simulator.
Actual practice, one-stop-shop arrangements and locally requested documents may vary by municipality and Urban Agency. Check with them before filing.
Every requirement, article by article, with phase, document and responsible party: regulatory requirements matrix for construction in Morocco (in French, table and CSV).
Frequently asked questions
How long does a building permit take in Morocco?
Joint order 1839-23 of 2023 sets 15 days for small projects (housing up to ground + 3 floors and 15.50 m) and 30 days for major projects, counted from the receipt of a complete application. The clock restarts if amended plans are requested (RGC art. 41).
Do I need to be in Morocco to apply for a building permit?
No. The application can be filed by the owner, the architect or a mandated person (RGC art. 34); in practice the architect files online. Keep copies of the filing receipt, the committee minutes and the issued permit.
Is silence from the municipality a permit?
Article 48 of Law 12-90 deems the permit granted two months after filing without an answer. The project must still comply with planning rules: never start work without a written document.
What happens if the committee asks for changes?
You are informed by registered letter within 2 working days and the time limits only restart when corrected plans are filed (RGC art. 41). For a minor reservation, the architect has 5 working days (art. 42).
How long is a building permit valid?
One year: it lapses if foundation work has not started within a year of issue (Law 12-90, art. 49). No extension is provided; you must reapply.
Can I appeal a refusal from abroad?
Yes. The refusal must state its reasons. You can refile corrected plans, request a re-examination, or bring an action for abuse of power before the administrative court, in principle within 60 days of notification (Law 41-90), through a Moroccan lawyer.
Is the Urban Agency's opinion binding?
Yes. Under article 39 of the RGC, no permit can be issued without the Urban Agency's opinion, and the mayor must comply with it.
Reference texts (6)
- Loi n° 12-90 relative à l'urbanisme, dahir n° 1-92-31 du 15 hija 1412 (17 juin 1992), BO n° 4159 du 15 juillet 1992
- Loi n° 66-12 relative au contrôle et à la répression des infractions en matière d'urbanisme et de construction, dahir n° 1-16-124 du 25 août 2016 — traduction française BO n° 6770 du 18 avril 2019
- Décret n° 2-18-577 du 8 chaoual 1440 (12 juin 2019) approuvant le règlement général de construction, et arrêtés conjoints n° 337-20 et n° 338-20 — BO n° 6874 du 16 avril 2020 (édition française)
- Arrêté conjoint n° 1032-21 du 13 avril 2021 modifiant l'arrêté conjoint n° 337-20 (pièces des dossiers) — BO n° 6992 du 3 juin 2021
- Arrêté conjoint n° 1839-23 du 10 juillet 2023 fixant les délais de chaque intervenant pour certaines décisions d'urbanisme délivrées par les communes — BO n° 7212 du 13 juillet 2023 (édition arabe)
- Agence urbaine de Kénitra-Sidi Kacem — lois, décrets, arrêtés et circulaires d'urbanisme
Read next
- Building permit fees and taxes in Morocco: what the authorisations cost
- Building permit in Morocco: documents, steps and timelines
- Building permit in rural Morocco: rules, exemptions and procedure
- Rokhas: how online building permit applications work in Morocco
- Which laws govern urban planning and construction in Morocco?
Stay informed
Material prices, new planning rules and site advice: one letter a month, written by an architect.